Purchasing

Reorder point formula: how to calculate it, with examples

Ivan de Ramon4 min read

Reorder point formula: average daily demand times lead time in days plus safety stock
On this page

The reorder point formula is: reorder point = (average daily demand × lead time in days) + safety stock. When stock falls to this number, you place the next order. This guide explains each part, works through examples and gives you a calculator.

Reorder point calculator

Enter your daily demand, lead time and safety stock.

Your numbers

Use the same unit (eaches or cases) and the same kind of day for all three. Numbers only, up to 6 decimal places, no commas. Safety stock is the buffer you have chosen; the calculator does not pick it for you.

Reorder point: 170 units

Rounded up: 170 units.

Reorder when usable stock falls to this level. It is not the quantity to buy.

The reorder point formula

Reorder point = (average daily demand × lead time in days) + safety stock

PartWhat it meansWhere to get it
Average daily demandUnits you sell or use per daySales of the last 30 to 90 days, divided by the number of days
Lead timeDays from placing the order until the stock is ready to sellYour last purchase orders: order date to receiving date
Safety stockExtra units for demand spikes and late deliveriesThe safety stock formula

The first part, average daily demand × lead time, is called lead time demand. It is what you expect to sell while you wait for the delivery.

Worked example

You sell 10 units a day. Your supplier takes 14 days. You hold 30 units of safety stock.

Lead time demand: 10 × 14 = 140 units

Reorder point: 140 + 30 = 170 units

When stock falls to 170 units, you order. If everything goes as planned, the delivery arrives when you are down to your 30 units of safety stock.

Reorder point without safety stock

Reorder point = average daily demand × lead time

In the example that is 140 units. Use it only when demand is very steady and the supplier is always on time. With no buffer, any busy week or late truck means a stockout.

Compare it with the right stock number

Do not compare the reorder point with the stock on the shelf. Compare it with your inventory position:

Inventory position = on hand + on order − backorders

Example. You have 150 units on hand, 200 on order and 20 promised to customers. Inventory position is 150 + 200 − 20 = 330. That is above 170, so you do not order, even though the shelf is below the reorder point. Without this step you order the same goods twice.

The formula when you order on fixed days

Some buyers do not order the moment stock hits a number. They review each supplier on a fixed day, for example every Monday. Then the stock has to last until the next review plus the lead time:

Order-up-to level = average daily demand × (lead time + days between reviews) + safety stock

Example. 10 units a day, 14 days lead time, a review every 7 days, 30 units of safety stock: 10 × (14 + 7) + 30 = 240 units. On each review day you order the difference between 240 and your inventory position.

Our post on periodic and continuous review compares the two ways of ordering.

Reorder point and min/max

In a min/max system the minimum is the reorder point. The maximum is the reorder point plus the order quantity. With a reorder point of 170 and an order quantity of 300, min is 170 and max is 470.

The reorder point tells you when to order. It does not tell you how much. For that, see the EOQ formula.

Common mistakes

  • Mixed units. Use eaches or cases for all three numbers, not a mix.
  • Lead time that ends when the truck arrives. Count until the stock is put away and ready to sell.
  • Old averages. A yearly average hides the season. Use recent sales, or a forecast for seasonal items.
  • Set once, never changed. Many ERPs still hold reorder points that somebody typed in years ago. Demand and suppliers have changed since then.
  • Ignoring open orders. Use the inventory position, as shown above.

When the formula is wrong

  • Seasonal items. The reorder point should rise before the high season and fall after it.
  • Slow or lumpy items. An average of 0.1 units a day says little. Use a fixed minimum or order when a customer asks.
  • Lead times that change a lot. The buffer has to cover that. Use formula 3 or 4 in the safety stock guide.

For a full catalog, inventory optimization software sets the reorder point of every item from a forecast and updates it when demand or lead times change.

Frequently asked questions

What is the reorder point formula?

Reorder point = (average daily demand × lead time in days) + safety stock. Example: 10 units a day × 14 days + 30 units of safety stock = 170 units.

How do I calculate the reorder point in Excel?

Put average daily demand in A1, lead time in days in B1 and safety stock in C1. The formula is =A1*B1+C1.

What is the difference between reorder point and safety stock?

Safety stock is the buffer you hope you never use. The reorder point is the stock level that triggers an order. Safety stock is one part of it.

What is the difference between reorder point and reorder quantity?

The reorder point is when you order. The reorder quantity is how much you order. The EOQ formula is one way to set the quantity.

How often should I update reorder points?

At least every quarter, and whenever demand, lead time or the supplier changes. Fast-moving items deserve a monthly check.